Schedule Outage


Maintenance Shutdown Schedule


The augmentation and maintenance work will be carried out in the areas mentioned below to ensure an uninterrupted power supply and no equipment failure / breakdown. Due to this, the Electricity supply may be affected in the following areas on
01/10/2022
S. NoDisttZoneDESCRIPTIONDate Time fromDate Time toArea affectedTotal Duration (in Hrs)
1 BAWANA 521 PROJECT WORK 01.10.22 08:00 01.10.22 16:00 PART OF J BLK SEC 5 8
2 BAWANA 521 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00 PART OF G 196 SEC 2 6
3 BAWANA 521 PREVENTIVE MAINTENANCE 01.10.22 11:00 01.10.22 14:00 PART OF C BLK SEC 2 3
4 BAWANA 521 PROJECT WORK 01.10.22 07:00 01.10.22 13:00 PART OF H/3 6
5 BAWANA 521 PROJECT WORK 01.10.22 09:30 01.10.22 16:00 PART OF F/2 7
6 BAWANA 521 PROJECT WORK 01.10.22 09:30 01.10.22 16:00 PART OF I, I1 SEC 5 7
7 BAWANA 521 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00 PART OF F BLK SEC 1 6
8 BAWANA 533 PROJECT WORK 01.10.22 08:30 01.10.22 13:00 PART OF DUSIB 5
9 BAWANA 533 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00  PART OF KANJHAWLA 6
10 KESAHAVPURAM 501 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00 PART OF G BLOCK INDL AREA 6
11 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 01.10.22 14:00 01.10.22 16:00 PART OF H-BLK JJ COLONY 2
12 MODEL TOWN 402 PREVENTIVE MAINTENANCE 01.10.22 11:00 01.10.22 13:00 PART OF A- BLK DERAWALA 2
13 MODEL TOWN 505 PREVENTIVE MAINTENANCE 01.10.22 10:30 01.10.22 14:30 PART OF A BLK 4
14 MOTI NAGAR 1303 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00 PART OF B BLOCK SUDERSHAN PARK 6
15 NARELA 511 PROJECT WORK 01.10.22 10:30 01.10.22 16:00 PART OF DARSHAN VIHAR 6
16 NARELA 514 PREVENTIVE MAINTENANCE 01.10.22 11:00 01.10.22 15:00 PART OF BHORGARH INDUSTRIAL AREA PH-2 4
17 NARELA 514 PROJECT WORK 01.10.22 11:00 01.10.22 15:00 PART OF BHORGARH INDUSTRIAL AREA PH-2(WEEKLY OFF) 4
18 NARELA 522 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00 PART OF J-2799 TO J-2809 AND J-2870 TO J-3012 6
19 NARELA 522 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 16:00 PART OF B-2619 TO B-2646 6
20 NARELA 522 PREVENTIVE MAINTENANCE 01.10.22 10:00 01.10.22 15:00 PART OF I-2266 TO I-2276 AND I-2288 TO I-2290 AND I BLOCK GAS GODOWN 5
21 NARELA 522 METERING WORK 01.10.22 10:30 01.10.22 16:00 PART OF A-270 TO A-304 DSIIDC 6
22 NARELA 522 METERING WORK 01.10.22 10:30 01.10.22 15:30 PART OF C-462 TO C-483 5
23 PITAMPURA 510 PROJECT WORK 01.10.22 08:00 01.10.22 11:00 PART OF MULTANI MOHALLA 3
24 PITAMPURA 530 PREVENTIVE MAINTENANCE 01.10.22 11:00 01.10.22 12:00 PART OF KOHAT KIOSK-1 1
25 ROHINI 551 PREVENTIVE MAINTENANCE 01.10.22 11:30 01.10.22 15:00 PARTS OF VIJAY VIHAR-2 4
26 ROHINI 561 PREVENTIVE MAINTENANCE 01.10.22 11:00 01.10.22 13:00 PART OF VIJAY VIHAR 2
27 ROHINI 561 PREVENTIVE MAINTENANCE 01.10.22 14:00 01.10.22 16:00 PART OF VIJAY VIHAR PH-1 2
28 ROHINI 581 METERING WORK 01.10.22 11:30 01.10.22 13:30 PARTS OF BADLI 2
29 ROHINI 581 PREVENTIVE MAINTENANCE 01.10.22 10:30 01.10.22 12:30 PART OF PARADIZE APTT. 2
30 ROHINI 581 PREVENTIVE MAINTENANCE 01.10.22 14:00 01.10.22 16:00 PART OF PARADAIZE APTT. 2
31 SHALIMARBAGH 414 PREVENTIVE MAINTENANCE 01.10.22 11:00 01.10.22 15:00 PART OF KAUSHIK ENCLAVE 4
32 SHALIMARBAGH 532 PREVENTIVE MAINTENANCE 01.10.22 11:30 01.10.22 13:30 PART OF WAZIRABAD GALI NO-12,14,16 2