Schedule Outage


Maintenance Shutdown Schedule


The augmentation and maintenance work will be carried out in the areas mentioned below to ensure an uninterrupted power supply and no equipment failure / breakdown. Due to this, the Electricity supply may be affected in the following areas on
28/01/2021
S. NoDisttZoneDESCRIPTIONDate Time fromDate Time toArea affectedTotal Duration (in Hrs)
1 BAWANA 512 PROJECT WORK 28.01.21 10:30 28.01.21 16:00 PART OF BAWANA VILL 6
2 BAWANA 521 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 12:30 PART OF A BLOCK SEC 5 2
3 BAWANA 521 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 12:30 PART OF A BLOCK SEC 5 2
4 BAWANA 521 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 12:30 PART OF A BLOCK SEC 5 2
5 BAWANA 521 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 12:30 PART OF A BLOCK SEC 5 2
6 BAWANA 521 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 15:29 PART OF A BLOCK SEC 5 5
7 BAWANA 521 PREVENTIVE MAINTENANCE 28.01.21 13:30 28.01.21 15:30 PART OF A BLOCK SEC 5 2
8 BAWANA 533 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 12:30 PART OF SAWADA VILLAGE 1
9 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 12:30 PART OF B-2/15 PH 2 2
10 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 28.01.21 10:45 28.01.21 13:45 PART OF B-1, B-2 AND B-4 BLK PH 2 3
11 KESAHAVPURAM 520 PREVENTIVE MAINTENANCE 28.01.21 15:00 28.01.21 16:00 PART OF RAMPURA 1
12 KESAHAVPURAM 520 PREVENTIVE MAINTENANCE 28.01.21 11:30 28.01.21 12:30 PART OF RAMPURA 1
13 MANGOLPURI 518 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 13:00 PART OF T- BLK M. PURI PARTIALY 2
14 MANGOLPURI 519 PROJECT WORK 28.01.21 11:00 28.01.21 15:00 PART OF BUDH VIHAR PH-1 4
15 MANGOLPURI 519 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 15:00 PART OF PKT-5 SEC-22 4
16 MANGOLPURI 523 PROJECT WORK 28.01.21 11:00 28.01.21 15:00 PART OF D-BLK PRATAP VIHAR-3 4
17 MODEL TOWN 402 PREVENTIVE MAINTENANCE 28.01.21 11:30 28.01.21 13:30 PART OF AZADPUR VILLAGE 2
18 MODEL TOWN 402 PREVENTIVE MAINTENANCE 28.01.21 11:30 28.01.21 13:30 PART OF AZADPUR VILLAGE 2
19 MODEL TOWN 412 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 13:00 PART OF TAGORE PARK 2
20 MODEL TOWN 413 PREVENTIVE MAINTENANCE 28.01.21 14:00 28.01.21 16:00 PART OF PERMA NAND AREA 2
21 MODEL TOWN 415 PROJECT WORK 28.01.21 10:00 28.01.21 16:00 PART OF ROAD NO 51 6
22 MOTI NAGAR 1301 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 13:00 PART OF N BLOCK KIRTI NAGAR 2
23 MOTI NAGAR 1302 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 13:30 PART OF A BLK NARAINA VIHAR 3
24 MOTI NAGAR 1302 PREVENTIVE MAINTENANCE 28.01.21 13:30 28.01.21 16:00 PART OF A BLK NARAINA VIHAR 3
25 MOTI NAGAR 1303 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 13:00 PART OF 9 BLOCK RAMESH NAGAR 2
26 NARELA 511 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 12:30 PART OF BUDHPUR 1
27 NARELA 511 PREVENTIVE MAINTENANCE 28.01.21 14:00 28.01.21 15:00 PART OF BUDHPUR 1
28 NARELA 511 PREVENTIVE MAINTENANCE 28.01.21 15:00 28.01.21 16:00 PART OF BUDHPUR 1
29 NARELA 511 PREVENTIVE MAINTENANCE 28.01.21 09:30 28.01.21 11:00 PART OF BUDHPUR 2
30 NARELA 511 PREVENTIVE MAINTENANCE 28.01.21 10:30 28.01.21 14:30 PART OF ALIPUR 4
31 NARELA 511 PREVENTIVE MAINTENANCE 28.01.21 12:00 28.01.21 13:30 PART OF BUDHPUR 1
32 NARELA 511 PROJECT WORK 28.01.21 14:00 28.01.21 16:00 PART OF MAUKHMELPUR 2
33 NARELA 514 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 15:00 PART OF PREM COLONY(A/R AT POLE NO. HT514-42/41 OPAN & P.NO.3 CLOSED AT PULIYA WALA PL/M S/S) 4
34 NARELA 517 PREVENTIVE MAINTENANCE 28.01.21 10:00 28.01.21 16:00 PART OF PALLA ,MAZRA 6
35 PITAMPURA 504 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 13:00 PART OF BANK VIHAR 2
36 PITAMPURA 504 PREVENTIVE MAINTENANCE 28.01.21 11:00 28.01.21 13:00 PART OF BANK VIHAR 2
37 PITAMPURA 504 PREVENTIVE MAINTENANCE 28.01.21 14:00 28.01.21 16:00 PART OF RAIL VIHAR 2
38 PITAMPURA 504 PREVENTIVE MAINTENANCE 28.01.21 14:00 28.01.21 16:00 PART OF RAIL VIHAR 2
39 PITAMPURA 508 PREVENTIVE MAINTENANCE 28.01.21 14:00 28.01.21 16:00 PART OF LD BLK 2
40 SHALIMARBAGH 414 PREVENTIVE MAINTENANCE 28.01.21 11:30 28.01.21 15:30 PART OF IP COLONY + KAUSHIK ENCLAVE 4
41 SHALIMARBAGH 503 PROJECT WORK 28.01.21 10:30 28.01.21 13:30 PART OF SUKLA COLONY ETC 3
42 SHALIMARBAGH 532 PROJECT WORK 28.01.21 10:00 28.01.21 16:00 PART OF JAGATPUR 6