Schedule Outage


Maintenance Shutdown Schedule


The augmentation and maintenance work will be carried out in the areas mentioned below to ensure an uninterrupted power supply and no equipment failure / breakdown. Due to this, the Electricity supply may be affected in the following areas on
03/12/2021
S. NoDisttZoneDESCRIPTIONDate Time fromDate Time toArea affectedTotal Duration (in Hrs)
1 BADLI 507 PROJECT WORK 03.12.21 10:00 03.12.21 16:00 PART OF GALI NO -6 SIRASPUR GURUDWARA ROAD 6
2 BADLI 572 PROJECT WORK 03.12.21 12:00 03.12.21 14:00 PART OF ALPIR 2
3 BAWANA 512 PROJECT WORK 03.12.21 10:30 03.12.21 16:00 PART OF BAWANA 6
4 BAWANA 521 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF P BLK SEC 5 2
5 BAWANA 521 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF P BLK SEC 5 2
6 BAWANA 521 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF P BLK SEC 5 2
7 BAWANA 521 PREVENTIVE MAINTENANCE 03.12.21 13:30 03.12.21 15:30 PART OF N BLK SEC 2 2
8 BAWANA 521 PREVENTIVE MAINTENANCE 03.12.21 13:30 03.12.21 15:30 PART OF N BLK SEC 5 2
9 BAWANA 521 PREVENTIVE MAINTENANCE 03.12.21 13:30 03.12.21 15:30 PART OF P BLK SEC 5 2
10 CIVIL LINES 411 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 16:00 PART OF MONESTY AREA 5
11 CIVIL LINES 411 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 15:00 PART OF MONESTY 4
12 CIVIL LINES 417 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PARTIAL AREA OF KAMLA NAGAR 2
13 CIVIL LINES 417 PREVENTIVE MAINTENANCE 03.12.21 12:30 03.12.21 14:30 PARTIAL AREA OF KAMLA NAGAR. 2
14 CIVIL LINES 417 PREVENTIVE MAINTENANCE 03.12.21 14:30 03.12.21 16:30 PARTIAL AREA OF KAMLA NAGAR 2
15 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF A2 2
16 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 03.12.21 14:30 03.12.21 16:30 PART OF A15 2
17 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF A5 2
18 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF A9/3 2
19 KESAHAVPURAM 502 PREVENTIVE MAINTENANCE 03.12.21 14:30 03.12.21 16:30 PART OF A12 2
20 MANGOLPURI 515 PROJECT WORK 03.12.21 11:00 03.12.21 13:00 PART OF P & Q BLK MGP 2
21 MANGOLPURI 518 PROJECT WORK 03.12.21 11:00 03.12.21 13:00 PART OF D-6 S.PURI PARTIALLY 2
22 MANGOLPURI 519 PREVENTIVE MAINTENANCE 03.12.21 14:00 03.12.21 16:00 PART OF PKT-9 SEC-21 HVDS 2
23 MANGOLPURI 519 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 13:00 PART OF SEC-20 2
24 MODEL TOWN 415 PREVENTIVE MAINTENANCE 03.12.21 11:30 03.12.21 13:30 PART OF SARAI PIPAL THALA 2
25 MODEL TOWN 505 PREVENTIVE MAINTENANCE 03.12.21 10:00 03.12.21 16:00 PART OF D BLK HVDS 6
26 MOTI NAGAR 1304 PREVENTIVE MAINTENANCE 03.12.21 13:30 03.12.21 16:00 PART OF C BLK INDERPURI STN 3
27 MOTI NAGAR 1304 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 13:00 PART OF C BLK INDERPURI 3
28 NARELA 511 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 13:00 PART OF SUSHANT VIHAR 2
29 NARELA 514 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 13:00 PART OF BANKNER VILLAGE 2
30 NARELA 514 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 13:00 (PARTIAL BACKFEED)PART OF SWATANTAR NAGAR PART-B 2
31 NARELA 514 PREVENTIVE MAINTENANCE 03.12.21 14:00 03.12.21 16:00 PART OF BANKNER VILLAGE 2
32 NARELA 514 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 13:00 PART OF BANKNER VILLAGE 2
33 NARELA 514 PREVENTIVE MAINTENANCE 03.12.21 14:00 03.12.21 16:00 PART OF BANKNER VILLAGE 2
34 NARELA 517 PREVENTIVE MAINTENANCE 03.12.21 10:00 03.12.21 16:00 PART OF BAKHTAWARPUR 6
35 NARELA 522 PREVENTIVE MAINTENANCE 03.12.21 07:15 03.12.21 10:00 PART OF A-307 TO A-309 3
36 NARELA 522 PREVENTIVE MAINTENANCE 03.12.21 07:00 03.12.21 10:00 PART OF A-311 3
37 PITAMPURA 504 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF BA 13 2
38 PITAMPURA 504 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF BA 16 2
39 PITAMPURA 504 PREVENTIVE MAINTENANCE 03.12.21 14:00 03.12.21 16:00 PART OF A-50 MIA PH-2 2
40 PITAMPURA 504 PREVENTIVE MAINTENANCE 03.12.21 14:00 03.12.21 16:00 PART OF A-54 2
41 PITAMPURA 530 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF KAPIL VIHAR & KOHAT ENCLAVE 2
42 ROHINI 561 PREVENTIVE MAINTENANCE 03.12.21 11:30 03.12.21 13:30 PARTIALLY GOLDEN JUBLI APPT. & RG MALL COMPLEX SEC-11 2
43 ROHINI 581 PREVENTIVE MAINTENANCE 03.12.21 10:30 03.12.21 12:30 PART OF F BLOCK SEC 18 2
44 ROHINI 581 PREVENTIVE MAINTENANCE 03.12.21 14:00 03.12.21 16:00 PART OF F BLOCK SEC 18 2
45 SHALIMARBAGH 503 PREVENTIVE MAINTENANCE 03.12.21 11:00 03.12.21 15:00 PART OF MUKUNDPUR 4
46 SHALIMARBAGH 532 METERING WORK 03.12.21 11:00 03.12.21 14:00 PART OF RAMGHAT 3