Connection Procedure

The consumer shall submit an application, seeking connectivity under the Net Metering Regulations, 2014 in the specified format as per Annexure – I along with an application fee of Rs. 500/- (Rupees Five Hundred) to Tata Power-DDL for feasibility analysis.

Tata Power-DDL shall acknowledge the receipt of the application form along with fee and shall record time, date & serial number of the receipt that shall form the basis for drawing the priority list.

In order of priority, Tata Power-DDL shall complete the feasibility analysis for connecting the Renewable Energy System to the distribution system within thirty (30) days from the date of receipt of the application.

On feasibility analysis, if it is found feasible for Tata Power-DDL to provide connectivity for the applied capacity or a reduced capacity, Tata Power-DDL shall inform all such applicants, to apply for registration and further processing.

The rooftop solar plant must get connected to the grid within one year from the registration process.

The procedure for connectivity of Renewable Energy System under Regulation 6 of Net Metering Regulations, 2014 is a three tier process, which is as follows;

i) Feasibility Analysis
ii) Registration
iii) Connection Agreement