18.01.2017
S. NoDisttZoneDESCRIPTIONDate Time fromDate Time toArea affectedTotal Duration (in Hrs)
1 BADLI 507 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 05:00 A PART OF SHAKTI BHOG WALI GALI AND MAIN MARKET SAMAYPUR 7
2 BADLI 581 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 02:00 PART OF B BLOCK SEC-18 4
3 BAWANA 512 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 05:00 PARTS OF VILLAGE QUTUBGARDH 6
4 BAWANA 513 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 03:00 PART OF SUKHBEER NAGAR HVSD AREA 4
5 BAWANA 533 PROJECT WORK 18.01.17 11:00 18.01.17 05:00 JYONTI,TATESHAR JHIMARPURA 6
6 CIVIL LINES 424 PROJECT WORK 18.01.17 11:00 18.01.17 03:00 PART OF ARYA PURA NEAR MATA MARKET,CHAMANGANJ,ROSHANARA CLUB SIDE, 4
7 KESAHAVPURAM 501 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 05:20 SOME PART OF C BLOCL I.E C-37/2, C-37/3 TO C-37/8. 7
8 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 18.01.17 02:00 18.01.17 06:00 NEAR B-30/1 WPIA 4
9 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 18.01.17 02:00 18.01.17 06:00 NEAR B-3 GROUP WPIA 4
10 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 18.01.17 09:35 18.01.17 01:45 NEAR B-85 WPIA 4
11 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 18.01.17 09:40 18.01.17 01:45 NEAR B-20/1 WPIA 4
12 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 18.01.17 09:45 18.01.17 01:45 NEAR B-82 WPIA 4
13 KESAHAVPURAM 509 PREVENTIVE MAINTENANCE 18.01.17 09:50 18.01.17 01:45 NEAR B-73 WPIA 4
14 KESAHAVPURAM 509 PPROJECT WORK 18.01.17 09:30 18.01.17 05:30 PART OF C-BLOCK WPIA 8
15 MANGOLPURI 515 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 03:00 PART OF S BLK 4
16 MANGOLPURI 518 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 02:00 PARTS OF H1 BLK 4
17 MANGOLPURI 518 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 02:00 PARTS OF H1 BLK 4
18 MANGOLPURI 518 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 04:00 PARTS OF C 10 BLK P1 BLK 6
19 MANGOLPURI 519 PREVENTIVE MAINTENANCE 18.01.17 02:00 18.01.17 05:00 PART OF KRISHAN VIHAR 3
20 MANGOLPURI 519 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 01:30 PART OF HARSH DEV PARK 3
21 MANGOLPURI 523 METERING WORK 18.01.17 03:00 18.01.17 05:00 PART OF KARAN VIHAR AND PART OF BALVEER VIHAR 2
22 MANGOLPURI 523 METERING WORK 18.01.17 12:00 18.01.17 02:00 PART OF SINGH ENCLAVE,PART OF ADARSH ENCLAVE AND PREM NGAR 2
23 MODEL TOWN 402 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 03:00 PART OF A BLK GTK 4
24 MOTI NAGAR 1304 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 02:00 PART OF SOUTH PATEL NAGAR, RANJIT NAGAR 4
25 NARELA 514 PROJECT WORK 18.01.17 11:00 18.01.17 03:00 PART OF SAWTANTAR NAGAR PART A AND PART B 4
26 NARELA 514 PROJECT WORK 18.01.17 10:30 18.01.17 02:30 PART OF SAWTANTAR NAGAR PART-B 4
27 NARELA 517 PROJECT WORK 18.01.17 11:00 18.01.17 05:30 PART OF BAKHTAWAR PUR 6
28 NARELA 517 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 05:30 PART OF TIKRI 6
29 NARELA 522 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 05:00 B BLOCK B2 DDA 7
30 NARELA 522 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 05:00 B BLOCK OF DDA B2 NRL 7
31 NARELA 522 PREVENTIVE MAINTENANCE 18.01.17 05:15 18.01.17 09:30 E-860 TO E-871 4
32 NARELA 522 PREVENTIVE MAINTENANCE 18.01.17 05:15 18.01.17 09:30 J-3205 TO J-3369 4
33 NARELA 522 PREVENTIVE MAINTENANCE 18.01.17 05:15 18.01.17 09:30 PART OF C BLOCK 4
34 PITAMPURA 508 PREVENTIVE MAINTENANCE 18.01.17 01:30 18.01.17 03:30 PARTS OF KASTURBA POLYTECHNIC 2
35 PITAMPURA 508 PREVENTIVE MAINTENANCE 18.01.17 01:30 18.01.17 03:30 PARTS OF KASTURBA POLYTECHNIC 2
36 PITAMPURA 530 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 11:00 HIG-A,B,C,D,E,F,G BLOCK 1
37 PITAMPURA 530 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 11:00 M2/C,M3/C,M3/B,M5/A,M5/D-MIG FLATS 1
38 ROHINI 551 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 12:00 PKT -6 ,SEC-2 2
39 ROHINI 551 PREVENTIVE MAINTENANCE 18.01.17 02:00 18.01.17 04:00 PKT-6,SEC-2 2
40 ROHINI 561 PREVENTIVE MAINTENANCE 18.01.17 02:00 18.01.17 05:30 PART OF RITHALA 3
41 ROHINI 561 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 01:30 PART OF RITHALA 3
42 ROHINI 571 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 03:00 RAJAPUR VILLAGE, SEC-9 ROHINI 4
43 SHAKTI NAGAR 422 PROJECT WORK 18.01.17 10:30 18.01.17 06:00 ANAND NAGAR 8
44 SHAKTI NAGAR 423 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 03:00 PART OF DHOBI WALI GALI, GHODE WALI GALI, GAUSHALA ROAD 4
45 SHAKTI NAGAR 423 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 03:00 PART OF GALI GHODE WALI, GAUSHALA ROAD AND DHOBI WALA ROAD 4
46 SHALIMARBAGH 414 METERING WORK 18.01.17 11:30 18.01.17 03:30 PART OF BURARI VILLAGE 4
47 SHALIMARBAGH 414 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 02:30 PART OF WEST KAMAL VIHAR. 4
48 SHALIMARBAGH 414 PREVENTIVE MAINTENANCE 18.01.17 11:00 18.01.17 02:00 GAIL S/STN 3
49 SHALIMARBAGH 503 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 05:00 SSI INDUSTRAILA AREA. 7
50 SHALIMARBAGH 503 PREVENTIVE MAINTENANCE 18.01.17 10:00 18.01.17 05:00 SSI INDUSTRIAL AREA. 7
51 SHALIMARBAGH 505 PROJECT WORK 18.01.17 09:30 18.01.17 05:30 PART OF E-BLOCK JAHANGIR PURI 8
52 SHALIMARBAGH 531 PREVENTIVE MAINTENANCE 18.01.17 12:00 18.01.17 03:00 PART OF HAIDERPUR INDS. AREA. 3
53 SHALIMARBAGH 531 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 02:30 PART OF SHALAMAR INDS. AREA. 4
54 SHALIMARBAGH 531 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 02:40 PART OF SHALAMAR INDS. AREA. 4
55 SHALIMARBAGH 531 PREVENTIVE MAINTENANCE 18.01.17 10:30 18.01.17 04:30 SHALAMAR VILLAGE AND INDUSTRIAL AREA 6
56 SHALIMARBAGH 532 PROJECT WORK 18.01.17 12:00 18.01.17 03:00 RAMGHAT AND WZB GALI NO.09 3
57 SHALIMARBAGH 532 PROJECT WORK 18.01.17 10:00 18.01.17 05:00 HARIJAN BASTI, HARDEV NAGAR & PART OF SANGAM VIHAR 7
58 SHALIMARBAGH 532 PROJECT WORK 18.01.17 10:00 18.01.17 05:00 PART OF HARDEV NAGAR, JHARODA DAIRY & 7
59 NARELA 514 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 PART OF PREM COLONY 4
60 MANGOLPURI 523 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF GAURAV NAGAR/RAMESH ENCLAVE/AMAN VIHAR/ HARI NAGAR 4
61 MANGOLPURI 515 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 PART OF H BLK MANGOL PURI 4
62 BAWANA 513 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 PART OF SAWDA  4
63 KESAHAVPURAM 501 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF RAMPURA VILLAGE 4
64 MANGOLPURI 518 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF SULTAN PURI 4
65 KESAHAVPURAM 509 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 10:00 18.01.17 14:00 WAZIRPUR INDUSTRIAL AREA B & C BLOCK, GROUP IND. AREA WZP 4
66 NARELA 517 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF KHAM PUR 4
67 SHALIMARBAGH 505 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF MAHENDRA PARK 4
68 SHALIMARBAGH 505 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF JEHANGIR PURI 4
69 SHALIMARBAGH 505 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 PART OF SANJAY NAGAR 4
70 MANGOLPURI 519 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF BEGUM PUR 4
71 MANGOLPURI 515 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 PART OF J BLK MANGOL PURI 4
72 BAWANA 512 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 10:00 18.01.17 14:00 PART OF AUCHANDI VILLAGE 4
73 BADLI 516 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 10:00 18.01.17 14:00 PART OF SHAHBAD DAIRY 4
74 NARELA 514 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF SWANTANTAR NAGAR 4
75 BAWANA 513 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF JAIN NAGAR AND RAJEEV NAGAR. 4
76 KESAHAVPURAM 520 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 10:00 18.01.17 14:00 HARIZAN BASTI, KANHAIYA NAGAR, HANSA PURI, ONKAR NAGAR A,B & C, RAMPURA VILLAGE 4
77 ROHINI 551 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF VIJAY VIHAR 4
78 ROHINI 551 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF SANJAY ENCLAVE 4
79 MANGOLPURI 519 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF BUDH VIHAR 4
80 MANGOLPURI 519 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 PART OF ROHINI-SEC-20 AND 21. 4
81 BAWANA 512 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF BAWANA VILLAGE 4
82 KESAHAVPURAM 502 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 18:00 18.01.17 22:00 NIMRI COLONY, BHARAT NAGAR, WAZIRPUR JJ COLONY, WAZIRPUR VILLAGE 4
83 NARELA 511 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 16:00 18.01.17 20:00 PART OF SWAROOP NAGAR 4
84 PITAM PURA 530 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF L & M BLOCK OF SHAKURPUR JJ COLONY 4
85 NARELA 514 TENTATIVE SYTSTEM MAINTENANCE 18.01.17 06:00 18.01.17 10:00 PART OF GHOGHA VILLAGE 4